How to count insulation panels, fixings and adhesive

Updated October 16, 2026

Insulation is ordered from the area to cover. The panels follow from the area and their size, the consumables from the rates the maker gives. This guide counts quantities; it does not tell which thickness a building needs.

1. Area to insulate

For a roof or a floor, multiply the length by the width. For a wall, multiply the length by the height and subtract the doors and windows.

2. Panels, with waste

Increase the area by the waste for cuts, divide by the area of one panel and round up to a whole panel. A 60 × 120 cm panel covers 0.72 m².

3. Fixings, adhesive and vapour barrier

Fixings and adhesive are counted per square metre at the rate the maker gives. The vapour barrier covers the area plus its overlaps, when the build-up needs one.

Worked example: wall 12 × 2.8 m, 6 m² of openings

Panels 60 × 120 cm, 50 mm thick, 8 % waste, 6 fixings and 4 kg of adhesive per m², 10 % overlap:

  • Area 12 × 2.8 − 6 = 27.6 m².
  • Panels: 27.6 × 1.08 / 0.72 = 41.4, so 42 panels.
  • Fixings: 27.6 × 6 = 165.6, so 166. Adhesive: 27.6 × 4 = 110.4 kg.
  • Volume 27.6 × 0.05 = 1.38 m³. Vapour barrier 27.6 × 1.10 = 30.36 m².

Second case: a roof 10 × 8 m

Same panels, 8 % waste, without adhesive and without vapour barrier:

  • Area 10 × 8 = 80 m².
  • Panels: 80 × 1.08 / 0.72 = 120 exactly, so 120 panels, covering 86.4 m².
  • Fixings: 80 × 6 = 480. Volume 80 × 0.05 = 4 m³.
  • A roof needs no adhesive in this method: untick the vapour barrier if your build-up has none.

What this does not cover

The count gives no thermal resistance or U-value. The thickness, the type of insulation, the condensation and the fire requirements come from a thermal study and the maker’s data.

General information, checked at the date shown. It does not replace advice from a professional for your situation.

Tools for this guide

Other guides

How to calculate VAT

Net to gross, gross to net, several rates, rounding: the formulas with examples.

BUILNORA

How to price a construction quote

Quantities, materials, labour, overheads and margin: the method to price a job and send a quote that protects you.

BUILNORA

How to count aluminium joinery

Frame and leaf profiles, glass, door sheets, shutter slats, extruded weight and cladding: the method to order, with an example.