1. Volume of the screed
Volume (m³) = area (m²) × thickness (m). Measure the thickness where the floor is lowest, not on average, and add about 5 % of waste.
- A bonded screed (on a clean slab) is usually thinner than a floating screed (on insulation).
- Follow the minimum thickness required for your floor type and the product used.
Using the tool step by step
The numbered marks on the screenshots follow the order in which you use the tool. The fields are filled with an example.

Step 1 Enter your values: dimensions, materials and options. 
Step 2 Read the results: quantities, costs and estimated durations, updated as you type. 
Step 3 After: the 3D rendering of the finished work (an illustration made by the tool, not a photo).
2. Materials per cubic metre
A traditional mix is often about 300 to 400 kg of cement per m³ of screed (350 kg is common), with roughly 1,400 kg of sand and around 200 litres of water, adjusted to obtain a damp, workable mortar.
Ready-to-use screed mixes and liquid (self-levelling) screeds have their own consumption per m² and per cm: read it on the bag or the technical sheet.
Worked example: 20 m², 5 cm thick
20 × 0.05 = 1.00 m³; with 5 % waste, 1.05 m³. At 350 kg/m³:
- Cement: 1.05 × 350 ≈ 368 kg, i.e. 8 bags of 50 kg.
- Sand: about 1,470 kg.
- Water: about 210 litres.
Before laying
Plan joints around the edges (perimeter strip) and respect the drying time before laying the floor covering: a common rule of thumb is about one week per centimetre for a traditional screed, but the product sheet prevails.
Then the tile calculator gives the tiles and boxes for the same room.
General information, checked at the date shown. It does not replace advice from a professional for your situation.