How to price a construction quote

Updated October 2, 2026

Most losses on a job are decided before it starts, in the quote: a forgotten item, quantities without waste, labour underestimated or a margin computed on the wrong base. Here is a simple method, item by item, that works for a small renovation as well as for a structural work package.

1. Break the job into items and measure

Split the work into packages (earthworks, structure, masonry, coatings, tiling, painting…) and each package into items with a unit: m³ of concrete, m² of wall, linear metres, units. Measure on site or on the plans and write the dimensions down: they justify your quantities if the client questions them.

2. Cost each item: materials, labour, equipment

For each item, compute a dry cost per unit:

  • Materials at your purchase price, plus waste (about 5 % for concrete, 10 % for tiles, 10–15 % for cuts and breakage).
  • Labour: hours per unit × loaded hourly cost of the team (wages and social charges).
  • Equipment and consumables: mixer, scaffolding, rental, fuel, small supplies.
  • Transport, waste removal and access constraints (floors, narrow streets).

3. Add overheads and margin

Overheads (vehicle, insurance, office, unpaid quoting time) are usually spread as a percentage of the dry cost, often 10 to 20 %. Then apply your margin. Be careful: a 20 % margin on the selling price is not +20 % on the cost; to keep 20 % of the price, divide the cost by 0.8 (coefficient 1.25).

Compare your unit prices with your last jobs: if a price is far below your usual one, an item is probably missing.

4. Write a quote that protects you

Describe each item precisely (brand, thickness, finish), state what is excluded, the start date and duration, the validity of the offer (30 days is common while material prices move) and the payment schedule: deposit at signature (often 30 %), progress payments, balance at handover. Ask for a dated signature with “good for agreement”.

General information, checked at the date shown. It does not replace advice from a professional for your situation.

Tools for this guide

Quote Generator

Prepare a clear quote or estimate for your client, with validity date, taxes and totals, ready as PDF.

BUILNORA

Concrete Calculator

Volume of concrete for slabs, footings and columns, with waste margin and cement, sand and gravel quantities.

Profit Margin Calculator

Find your profit and margin from cost and price, or the price you need for a target margin.

Other guides

How to calculate VAT

Net to gross, gross to net, several rates, rounding: the formulas with examples.