Worked example — Length of the facade 20 m, Height to reach 9 m, Working levels (with decks) 3
Facade area covered: 180.00 m² · Bays: 8 · Lifts (levels): 5 · Frames: 45 · Braces: 40 · Decks: 24 · Guardrails: 48 · Base jacks: 18 · Tie anchors: 15
Enter the length and the height of the facade, the bay length and the lift height of your system, and how many working levels carry decks. PRAXAO gives the bays and the lifts, the frames, the braces, the decks, the guardrails, the base jacks and the tie anchors. The bay length, lift height, braces, decks, rails and the area served by a tie are starting values to replace with the supplier’s system data. The tool counts components: it does not design the scaffold or check its load class, stability or tying pattern, which belong to a competent person.
Enter the dimensions to see the drawing.
Fill in the fields to see the result.
Preliminary estimate from the values entered: not a structural validation and not an execution plan. Check the local rules and the manufacturers’ data.
Your last inputs are kept in this browser.
Results are provided for information. Check tax rates and legal requirements that apply to you.
Facade area covered: 180.00 m² · Bays: 8 · Lifts (levels): 5 · Frames: 45 · Braces: 40 · Decks: 24 · Guardrails: 48 · Base jacks: 18 · Tie anchors: 15
No. The design, the load class, the stability, the tying pattern and the inspection belong to a competent person under the regulations in force.
There is one more frame line than bays, and one frame per lift: frames = (bays + 1) × lifts, with the bays and the lifts rounded up.
The lifts that carry a deck for people to work on. Only those get decks and guardrails in this count.
Bays, lifts, frames, braces, decks, guardrails, jacks and ties of a frame scaffold, with an example.
Labour cost of a task from the quantity, your productivity and the hourly wage: hours, days, cost per unit.
Truck loads, haulage days and cost to deliver a volume or weight of material from the truck payload and the distance.
How much paint you need for your walls and ceilings, minus doors and windows, for the number of coats you plan.